Solar connection and approval checks for SME shophouses

Updated Sources & method
AI-generated photorealistic image: Technician with closed blank equipment and plain paper in front of commercial rooftop solar modules (generative image — not a real photo)
Illustration; not a photograph of a specific product.
In this guide

Start with the premise and account, not a generic compliance promise

A shoplot solar proposal depends on the building, electrical installation, roof rights and the account used for the connection. This guide does not determine whether a particular installation can connect to a switchboard, use an energy-management system or meet an approval requirement. Ask the provider to inspect the actual site and identify the applicable authority and submission route in writing.

For a rented shop, obtain written landlord consent and clarify who may sign utility and programme documents. Do not assume that a tenant, building owner and electricity account holder are the same party.

Check the recorded programme rules

For non-domestic Solar ATAP in Peninsular Malaysia, the recorded guideline limits PV inverter output to no more than 100% of the premises’ Maximum Demand and total installation capacity to no more than 1,000 kW, subject to the utility’s network assessment [source]. The capacity limit is expressed as inverter AC output (kWac), not panel kWp [source].

Premises and account checks for a non-domestic Solar ATAP proposal.
Betulkex — programme item and recorded scope (compiled 7 October 2026; source dates remain as cited)What the cited rule saysWhat the shop must still confirm
Non-domestic limitUp to 100% of Maximum Demand and no more than 1,000 kW total, subject to network assessment. [source]Account demand, connection details and the utility's site assessment.
Capacity unitLimit is based on inverter kWac output; forms request declared capacity in kWac and kWp. [source]The proposed panel/inverter schedule and its stated calculations.
Application and feeApplication is through SEDA eATAP by an RPVSP; application fee is RM7.50 per kWac and is non-refundable whether approved or rejected. [source]Who submits, whether the fee is included in the contract, and which documents are needed.
Utility agreementTNB stamp duty is RM10 unless a legal exemption applies; the programme agreement term is at most 10 years from its start date. [source] [source]Whether an exemption applies and the account agreement's start/end dates.

These are recorded programme rules, not approval for a particular shop. Ask the provider to identify the application path and responsible parties in writing; the utility or relevant authority decides the site-specific connection and approval.

Compare two written proposals

Copy the same fields from each proposal. Mark an item “not stated” when the document does not answer it; do not fill gaps by assumption.

Non-domestic rules, capacity and fees to verify in a written proposal.
Betulkex — quote fieldProposal AProposal BDocument or decision owner to identify
Electricity account holder, roof permission and signing party________Account bill and landlord consent
Panel kWp and inverter model/output in kWac________Quote and single-line diagram
Application route, submitter and payer of each stated fee________Application records; separate programme fee from other contract charges
Connection point, protection, switchboard work and utility documents________Site assessment and utility/authority decision
Work included/excluded, system ownership and post-installation responsibility________Contract, work scope and written terms

This is a completeness check, not a finding that either proposal is eligible or can connect.

Put these items in the proposal

Ask for the system single-line diagram, panel kWp and inverter kWac, proposed point of connection, protection and shutdown arrangements, monitoring interface and any required switchboard changes. Have the provider identify the responsible designer and installer, the authority submissions included, the fees excluded, and who will obtain approvals.

If the shop uses refrigeration, lifts, motors or other critical equipment, provide operating schedules and ask how solar operation interacts with those loads. Request an outage and commissioning plan; do not accept a promise of uninterrupted operations without a site-specific method. Ask the provider to assess and document compatibility for the exact premises and equipment. The utility or relevant authority decides connection and approval; a provider quote is not that decision.